How to Apply Online for IESCO New Connection in Islamabad 2024
If you are planning to get a new electricity connection in Islamabad, the process has become much easier now with the introduction of online application systems. The Islamabad Electric Supply Company Limited (IESCO) provides the facility to apply for a new connection through their official website. By following a few simple steps and submitting the required documents, you can apply for a new IESCO connection online without the hassle of visiting the office in person. In this article, we will guide you on how to apply online for IESCO new connection in Islamabad.
The Islamabad Electric Supply Company Limited (IESCO) was established in 1998 with the aim of sharing the responsibilities, functions, and assets of WAPDA in Islamabad. Under the leadership of CEO Amjad Khan, IESCO is a Pakistani company that distributes and supplies electricity from Attock to Jhelum, serving over 3 million consumers and making life easier for over 25 million people in its service areas.
Related Article: Fesco Bill Online Check | Fesco Duplicate Bill Check Complete Guide 2024
If you’re looking to How to Apply Online for IESCO New Connection, the process is simple and can be done online. Just follow these steps:
- Visit the IESCO website and click on the “New Connection” tab.
- Read the instructions carefully and fill out the online application form. Make sure to provide accurate and complete information, including your personal details and the location where you need the new connection.
- Upload the required documents, such as your CNIC, meter reading, and property documents.
- After submitting your application, you will receive a reference number, which you should keep for future reference.
- The IESCO team will review your application and visit your location to conduct a feasibility study.
- Once the feasibility study is complete and all requirements are met, you will receive a demand notice.
- Pay the demanded amount and submit the payment receipt to the nearest IESCO office.
- After the payment is verified, the IESCO team will install the meter and activate the connection.
How to Apply Online for IESCO New Connection – Required Details
- To apply for a new IESCO connection in Islamabad, you will need to provide the following details:
- Name of the applicant
- Permanent Address
- Postal Address
- Phone Number
- Minimum Load
- Connection type
- Neighbor details
- Proof of ownership of your residence or commercial property, such as a transfer letter or registry of the place
- Proof that your residence or commercial property does not have an existing electricity connection and that there are no payments due
- If there is more than one owner of the property, all owners must hand over the power of attorney to the applicant, and the applicant must provide power of attorney from each owner
- Applicant’s attested CNIC copy
- If the application is for more than a single-phase meter, then two witness ID Card copies are required, and a copy of the tariff must be given to the applicant and both witnesses. The signing of two witnesses is not required if the type of connection is residential or commercial.
- If the applicant is a tenant, the owner of the property must provide a NOC.
How To Apply Online For Lesco Meter In Islamabad
If you’re looking to How To Apply Online For Lesco Meter In Islamabad, you can easily do so by following these steps:
- Click on the link to visit IESCO’s official website.
- Select “Apply New Connection” from the options provided.
- Carefully fill out the online application form, providing accurate and complete information.
- Once the form is completed, submit it online.
- Print out a copy of the application form.
- Gather all the required documents mentioned earlier and attach them to the form.
- Send the application form and the attached documents to the concerned IESCO office.
- Once your documents have been verified, you will receive a Demand Notice from IESCO.
- Pay the Demand Notice amount to the designated bank.
- Make a copy of the paid Demand Notice.
- Send the copy of the paid Demand Notice to the concerned IESCO office.
- Once your payment has been verified, a new electricity connection will be provided to you.
New Electricity Connection Charges in Islamabad
New electricity connection charges in Islamabad depend on the type of meter and the length of the service line required. The charges for a single-phase meter range from Rs. 4,000 to Rs. 16,000 depending on the length of the service line, while the charges for a three-phase meter range from Rs. 15,000 to Rs. 48,600. It is important to note that these charges are fixed costs and do not include any additional fees or charges that may be applicable.
Related Article: How To,MEPCO Bill Check Online | MEPCO Bill Calculator 2024 Pro Guide
Single Phase Meter – Fixed Cost
If you need a new single-phase meter, you will have to pay a fixed cost that varies depending on the length of the service line. Here’s a breakdown of the fixed costs:
- For a service line up to and including 40 meters in length, the cost is Rs. 4000.
- For a service line above 40 meters, up to and including 100 meters in length (with one span LT with Ant Conductor and one Pole), the cost is Rs. 4000 + Rs. 200 per meter above 40 meters.
- For a service line above 100 meters, up to and including 160 meters in length (with two span LT with Ant Conductor and two Poles), the cost is Rs. 16000 + Rs. 250 per meter above 100 meters.
Keep in mind that these costs apply to single-phase meters only. If you require a different type of connection or meter, the costs may vary. Be sure to confirm all costs with the IESCO team before proceeding with your application.
Three Phase Meter – Fixed Cost
For a three-phase meter connection, the fixed costs are as follows:
- For a service line length up to and including 40 meters, the cost is Rs. 15,000.
- For a service line length above 40 meters, up to and including 100 meters (with one span LT with Ant Conductor and one Pole), the cost is Rs. 15,000 + Rs. 260 per meter above 40 meters.
- For a service line length above 100 meters, up to and including 160 meters (with two span LT with Ant Conductor and two Poles), the cost is Rs. 30,600 + Rs. 300 per meter above 100 meters.
- For a service line length above 160 meters, up to and including 280 meters, the cost is Rs. 48,600 + Rs. 340 per meter above 160 meters.
Service Line Length | Single Phase Meter Fixed Cost | Three Phase Meter Fixed Cost |
---|---|---|
Up to and including 40 meters | Rs. 4000 | Rs. 15,000 |
Above 40 meters, up to and including 100 meters (with one span LT with Ant Conductor and one Pole) | Rs. 4000 + Rs. 200 per meter above 40 meters | Rs. 15,000 + Rs. 260 per meter above 40 meters |
Above 100 meters, up to and including 160 meters (with two span LT with Ant Conductor and two Poles) | Rs. 16,000 + Rs. 250 per meter above 100 meters | Rs. 30,600 + Rs. 300 per meter above 100 meters |
Above 160 meters, up to and including 280 meters | – | Rs. 48,600 + Rs. 340 per meter above 160 meters |
Note: For single-phase meters, fixed costs are only applicable for lengths of service lines up to and including 160 meters. For lengths above 160 meters, the cost will be determined based on a survey conducted by the IESCO.
FAQ
What is IESCO and what areas does it cover?
IESCO (Islamabad Electric Supply Company) is a Pakistani company that sells, distributes, and supplies electricity from Attock to Jhelum. It facilitates 3 million consumers directly and also eases the lives of 25 million-plus people living around its service areas.
What documents are required to apply for a new IESCO connection?
To apply for a new IESCO connection, you will need to provide documents such as proof of ownership of your residence or commercial property, your attested CNIC copy, and if the application is for more than a single-phase meter, then two witness ID card copies are required.
Can I apply for a new IESCO connection online?
Yes, you can apply for a new IESCO connection online through their official website. After filling out the application form, you will need to submit it online and then send a printed copy of the form along with the required documents to the concerned IESCO office.
How long does it take for a new connection to be approved?
The time it takes for a new connection to be approved by IESCO can vary depending on factors such as the completeness of the application, availability of resources, and workload of the company. Typically, it can take anywhere from a few weeks to a few months.
What are the fixed costs for a single-phase meter and a three-phase meter?
The fixed costs for a single-phase meter range from Rs. 4000 to Rs. 16,000 depending on the length of the service line, while the fixed costs for a three-phase meter range from Rs. 15,000 to Rs. 48,600 depending on the length of the service line.
What should I do if I am a tenant of the premises?
If you are a tenant of the premises, the owner of the property must provide a NOC (No Objection Certificate) in order for you to apply for a new IESCO connection.